Roadmap
The order of work from research to the off-season, with dates that follow the XSERIES-3 schedule.
Timeline
Read from top to bottom. The thin red bar is XSERIES-3 (23–24 Jan 2027). Every phase before it must finish on time. The numbered diamonds are the decision points below.
Nov 2026Dec 2026Jan 2027Feb 2027Mar 2027 →
Discovery1–15 Nov. Research validated with the client, answers to Open questions, official brand assets, scope decision
Strategy and design15–30 Nov. Final IA, wireframes, visual direction approved, initial design system
Phase 1 · Before the event: buildDec. XS-3 hub website, CMS, initial content, waitlist
Phase 1 · Before the event: launchEarly Jan. Website live, linked from the IG bio and highlights
Phase 2 · During the event: buildJan. Live companion, predictions, MVP vote
XSERIES-323–24 Jan. Live companion active, measurement
EvaluationFeb. KPI report, sponsor report, Phase 3 decision
Phase 3 · After the eventMar onward. Fan accounts, card collection, off-season content
Decision points4 decisions, see below
1234
Decision points
Four decisions that determine whether the next phase goes ahead. The numbers match the diamonds in the timeline.
- Mid-Nov 2026Phase 1 scope1
- Phase 1 scope and who owns the content
- Related to CMS and Content team
- End of Nov 2026Visual direction2
- Visual direction approved (Visual decision log)
- End of Dec 2026Live companion go/no-go3
- Live companion for XS-3, depending on who can enter data during the event
- Feb 2027Move on to fan accounts?4
- Whether to move on to fan accounts, based on Phase 1–2 data
- Related to Own audience Connected outside the season
Warning
There are fewer than 12 weeks between now and XS-3. If discovery runs late, prioritize Phase 1 and push the live companion to the next edition.
The main goal of each phase is in Goals: business, user, tech, the features per phase are in Features & priorities, and how to measure them is in KPIs & measurement.
Research basis
- XSERIES-3 runs on 23–24 Jan 2027 at Indonesia Arena: XSERIES-3 tickets, from GOERS. From 1 Nov 2026 to kickoff is 83 days, fewer than 12 weeks.
- The website is linked from the IG bio and highlights because IG is the main channel, and the bio link currently goes straight to GOERS: Digital touchpoints
- Who can enter live data during the event is not yet known (Real-time score data Live data operator).
- The length of each phase and the decision points are proposals from the design team, not yet validated with the client. Budget and deadline are not confirmed (Budget & deadline).